Downtown Des Plaines Streetscape Construction Underway

New curbs, gutters, outdoor furniture and more is planned for the Miner Street area in 2013.

Construction on downtown Des Plaines’ curb appeal broke ground last week, and the city published a tentative schedule to let residents know what to expect in the coming months.

The downtown Des Plaines streetscape project, which includes new curbs, gutters, outdoor furniture, planters and more, is expected to continue until Oct. 1, according to an announcement from the Public Works and Engineering Department. For posted in Patch’s Local Voices section.

Des Plaines budgeted approximately $2.8 million for streetscape construction work in 2013, which is part of a total $13.2 million budgeted for infrastructure improvements this year.

Find out what's happening in Des Plaineswith free, real-time updates from Patch.

Below is the tentative construction schedule published by the City of Des Plaines.

Area 1  South Side of Miner Street from Graceland to Lee Street

Find out what's happening in Des Plaineswith free, real-time updates from Patch.

Area 2  South Side of Miner Street from Lee to the Metra Station

April 1 to April 30, 2013

Traffic Control, Site Layout, Mobilization, Demolition/Removal of Existing, Sewer and Water, Irrigation, Electrical, Concrete Curb/Planter/Walk, Pavers.

Area 3  South Side of Miner Street from the Metra Station to Pearson Street.

May 1 to May 21, 2013

Traffic Control, Site Layout, Mobilization, Demolition/Removal of Existing, Sewer and Water, Irrigation, Electrical, Concrete Curb/Planter/Walk, Pavers.

Area 4  North Side of Miner Street from Pearson Street  to Metropolitan Way

Area 5  North Side of Miner Street & East Side of Lee Street from Metropolitan Way to Lee Street

Area 6  North Side of Miner Street & West Side of Lee Street & East Side of Graceland Avenue from Lee Street to Graceland

May 21 to July 3, 2013

Traffic Control, Site Layout, Mobilization, Demolition/Removal of Existing, Sewer and Water, Irrigation, Electrical, Concrete Curb/Planter/Walk, Pavers.

Area 7 Median Installation Miner Street Center from Lee Street to Pearson Street

Area 8 City Hall Plaza

July 3 to July 24, 2013

Traffic Control, Site Layout, Mobilization, Demolition/Removal of Existing, Sewer and Water, Irrigation, Electrical, Concrete Curb/Planter/Walk, Pavers.

All Areas

July 25 to September 25, 2013

Pavement Markings, Punch-list, Plantings and Furniture

For more stories, pictures, information and conversation, like Des Plaines Patch on Facebook.


Get more local news delivered straight to your inbox. Sign up for free Patch newsletters and alerts.

We’ve removed the ability to reply as we work to make improvements. Learn more here